PEACHAM ROAD Project:
- Completing paving of the first course completed Tuesday, July 13th.
- Next course to be completed prior to August 20 including aprons and driveway blending.
- Shoulder work will happen both between layers and after final layer has been placed.
OTHER PLANNED WORK:
- Walden Hill Road – ditching and drainage
- Coles Pond Road – ditching
- Penny Lane – stone lined ditches and drainage
- General road maintenance such as grading, mowing and sign work throughout the season.
- Various projects within town limits.